Question: Table 4 shows the activities, predecessors and time estimates (in months) for a work package of the project. Required: Draw a network diagram (using the
Table 4 shows the activities, predecessors and time estimates (in months) for a work package of the project.
Required:
- Draw a network diagram (using the activity-on-node method) for the project.
- Identify the critical path and calculate the expected duration to complete the project.
- Calculate the probability of completing the project in 28 months.
- Calculate the probability of completing the project in 24 months.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
