Question: table [ [ , 6 . 5 , , 1 1 ] , [ , 5 , A , 1 2 . 5 ]

\table[[,6.5,,11],[,5,A,12.5],[C,7,A,B,4],[B,4,None,0],[A,3,None,1]]
b. Every week of delay in the project costs your company $750. Suppose you know the following: (1) Activity E can be crashed by 1 week, at a cost of $1,750,(2) activity B can be crashed by 1.0 week, at a total cost of only $150; and (3) activity C can be crashed by 1 week, at a cost of $2,250.
Management should crash activity(-ies)
The company will save $ (Enter your response as a whole number.)