Question: Table 7 . 4 Predecess Time ( week s ) Activity or A 8 B A 6 C 4 D C 9 E A 1

Table 7.4 Predecess Time (week s) Activity or A 8 B A6 C 4 D C 9 E A 11 LL F B3 G D, E, F 1 Table 7.4, what is the latest finish time for activity C? Select one : A. week 4 B. week 10 week 6. week 8