Question: Table 7 . 4 table [ [ Activity , table [ [ Predecess ] , [ or ] ] , table [

Table 7.4
\table[[Activity,\table[[Predecess],[or]],\table[[Time(week],[s)]]],[A,--,8],[B,A,6],[C,--,4],[D,C,9],[E,A,11],[F,B,3],[G,D, E, F,1]]
Using Table 7.4, what is the slack associated with activity B?
Select one:
A.1 week
B.2 weeks
C.3 weeks
D. None of these is the correct activity slack for B.
 Table 7.4 \table[[Activity,\table[[Predecess],[or]],\table[[Time(week],[s)]]],[A,--,8],[B,A,6],[C,--,4],[D,C,9],[E,A,11],[F,B,3],[G,D, E, F,1]] Using Table 7.4, what is the