Question: Table 7 . 6 Activity Immediate Predecessor ( s ) Time ( weeks ) A - - 3 B - - 4 C - -
Table
Activity Immediate Predecessors Time weeks
A
B
C
D A
E A B
F A B C
G D E
H E
I E F
J G H I
K H I
L I
Using Table suppose activity I is delayed, taking eight days to complete instead of two days. Assume all other activity times remain the same. How much longer will the total project earliest completion time become?
Question Select one:
A
three or four days
B
one or two days
C
zero days
D
five or six days
Step by Step Solution