Question: Table 7 . 6 table [ [ , Immediate, ] , [ Activity , Predecessor ( s ) Time ( weeks ) , ]

Table 7.6
\table[[,Immediate,],[Activity,Predecessor(s) Time (weeks),],[A,--,3],[B,--,4],[C,--,2],[,,],[D,A,4],[E,A, B,5],[F,A, B, C,2],[,,],[G,D, E,1],[H,E,6],[I,E, F,2],[,,],[J,G, H, I,4],[K,H, I,3],[L,I,6]]
Using Table 7.6, what is the critical path for this project?
B-E-H-K
B-E-H-J
C-F-I-L
A-E-G-J
 Table 7.6 \table[[,Immediate,],[Activity,Predecessor(s) Time (weeks),],[A,--,3],[B,--,4],[C,--,2],[,,],[D,A,4],[E,A, B,5],[F,A, B, C,2],[,,],[G,D, E,1],[H,E,6],[I,E, F,2],[,,],[J,G, H,