Table 7.13 All activity times for the project are in weeks. Activity Predecessor Optimistic Most Likely Pessimistic
Fantastic news! We've Found the answer you've been seeking!
Question:
Table 7.13 All activity times for the project are in weeks. Activity Predecessor Optimistic Most Likely Pessimistic A -- 12 16 25 B -- 7 14 22 C -- 5 10 14 D A 15 18 25 E C 8 12 18 F B 9 12 15 G F 18 22 29 H D, E, G 15 19 27 Using Table 7.13, what is the probability that the project will be completed in 65 or fewer weeks?