Question: Table 7.8 Activity Predecessor Normal Time (days) Crashing Time (days) Crashing Cost/day A -- 5 1 $200 B -- 7 1 $500 C -- 5

Table 7.8 Activity Predecessor Normal Time (days) Crashing Time (days) Crashing Cost/day A -- 5 1 $200 B -- 7 1 $500 C -- 5 1 $200 D A 10 2 $300 E B 6 1 $400 F A, C 7 2 $650 G B 4 1 $500 H E, D, G 6 1 $350 Using Table 7.8, what is the activity with the greatest amount of slack? Question 8Select one: A. A B. B C. C D. D Jump to