Question: Table A. Success probabilities from simulation. (JCL stands for joint confidence level.) Time success Cost success Time-Cost success ( JCL ) Time-Cost failure Probability 57%
Table A. Success probabilities from simulation. (JCL stands for joint confidence level.)
| Time success | Cost success | Time-Cost success (JCL) | Time-Cost failure | |
| Probability | 57% | 26% | 15% | 32% |
Table C. Success probabilities from simulation. (JCL stands for joint confidence level.)
| Time success | Cost success | Time-Cost success (JCL) | Time-Cost failure | |
| Probabilities | 58% | 26% | 25% | 41% |
2.3Compare the success probabilities inTable A andTable C.
Describe the effects of time-cost correlation in activities on the project's success.
What happens when time-cost correlation in a project is substantial but ignored in project schedule and cost risk assessment?