Question: table [ [ Activity , Activity Time ( weeks ) , Immediate Predecessor ( s ) ] , [ A , 4 , -

\table[[Activity,Activity Time (weeks),Immediate Predecessor(s)],[A,4,-],[B,7,A],[C,9,B],[D,3,B],[E,14,D],[F,10,C, D],[G,11,F, E]]
a. Draw the network diagram.
b. Calculate the slack for each activity and determine the critical path. How long will the project take?
 \table[[Activity,Activity Time (weeks),Immediate Predecessor(s)],[A,4,-],[B,7,A],[C,9,B],[D,3,B],[E,14,D],[F,10,C, D],[G,11,F, E]] a. Draw the network diagram.