Question: table [ [ Activity , Description, table [ [ Immediate ] , [ Predecessor ] ] , table [ [ Time ]
tableActivityDescription,tableImmediatePredecessortableTimeweeksASurvey building site,,BDevelop initial design,,CObtain board approval,A BDSelect architect,CEEstablish budget,CFFinalize design,D EGObtain financing,EHHire contractor,F G
a Draw a project network. Submit a file with a maximum size of MB
Choose File no file selected
This answer has not been graded yet.
b Identify the critical path. Enter your answers as a commaseparated list.
c Develop the activity schedule for the project.
tableActivitytableEarliestStarttableLatestStarttableEarliestFinishtableLatestFinishSlackABCDEFG
The expected completion time is weeks, which is Select than year.