Question: table [ [ Activity , Description,Optimistic ( a ) , Most Probable ( m ) , Pessimistic ( b ) ] , [ A

\table[[Activity,Description,Optimistic (a),Most Probable (m),Pessimistic (b)],[A,Plan event,2,3,4],[B,Select location,2.5,2,6],[C,Decide on speakers & vendors,4,4,4],[D,Prepare & mail brochures,2,4,6],[E,Update web site,1.5,2.5,3.5],[F,\table[[],[vendors]],3.5,4,4.5],[G,Registration & hotel reservations,3,3,6],[H,Finalize last-minute details,2,5,5]]
Question 1
2 pts
The Expected Time for Activity C is
4 weeks
3 weeks
2 weeks
6 weeks
 \table[[Activity,Description,Optimistic (a),Most Probable (m),Pessimistic (b)],[A,Plan event,2,3,4],[B,Select location,2.5,2,6],[C,Decide on speakers & vendors,4,4,4],[D,Prepare

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!