Question: table [ [ Activity , Designation,Predecessor,Time in Days ] , [ Break down both machines,A , None, 3 ] , [ Clean machine 1

\table[[Activity,Designation,Predecessor,Time in Days],[Break down both machines,A,None,3],[Clean machine 1,B,A,2],[Clean machine 2,C,A,4],[Re-set machine 1,D,B,3],[Re-set machine 2,E,C,2],[Re-calibrate both machines,F,D and E,2],[Final test,G,F,4]]
Using the Single Time Estimate CPM procedure, what is the slack time of Task E?
0
1
2
3
4