Question: table [ [ Activity , Designation,Predecessor,Time in Days ] , [ Break down both machines,A , None, 3 ] , [ Clean machine 1
tableActivityDesignation,Predecessor,Time in DaysBreak down both machines,ANone,Clean machine BAClean machine CAReset machine DBReset machine ECRecalibrate both machines,FD and EFinal test,GF
Using the Single Time Estimate CPM procedure, what is the slack time of Task E