Question: table [ [ Activity ( from WBS ) , Activity No . , Predecessors, table [ [ Duration ] , [ ( days
tableActivity from WBSActivity NoPredecessors,tableDurationdaysDecide on colour to paint room,APrepare walls and ceiling,BA EtableBuy paint and materials forpreparation of walls & ceilingEAPaint ceiling,CB A EPaint walls,DB A EOrder new curtains,FA
a Draw a network for the data given in the Table above
b What arrows would be correct but unnecessary?