Question: table [ [ Activity Immediate Predecessor ( s ) , table [ [ Normal ] , [ Time ( weeks ) ] ]

\table[[Activity Immediate Predecessor(s),\table[[Normal],[Time (weeks)]],\table[[Normal],[Cost ($)]],\table[[Crash],[Time (weeks)]],\table[[Crash],[Cost ($)]],],[A,-,3,5,000,1,9,000],[B,-,7,3,000,5,6,000],[C,A,9,7,000,8,12,000],[D,A, B,11,8,000,9,14,000],[E,B,2,5,000,2,5,000],[F,D,8,1,000,5,7,000],[G,E, F,2,3,000,1,9,000],[H,G,8,3,500,7,4,500],[I,C, F,9,3,000,8,7,000]]
a. What is the critical path based on the normal time?
A.BDFGH
B. BDFI
C. BEGH
D. ADFGH
b. What is the project duration based on the normal times? weeks.
c. Calculate different project costs based on the normal times.
Total direct costs (total normal costs): $,
Total indirect costs: $
Total penalty costs: $
d. To reduce the project duration by 1 week, which activity should we crash to minimize the project costs?
A. Activity D
B. Activity G
C. Activity B
D. Activity A
E. Activity H
e. What are the various project costs after crashing the activity you selected in part (d)?
Total direct costs (total normal costs): $
Total indirect costs; $
Total penalty costs: $
 \table[[Activity Immediate Predecessor(s),\table[[Normal],[Time (weeks)]],\table[[Normal],[Cost ($)]],\table[[Crash],[Time (weeks)]],\table[[Crash],[Cost ($)]],],[A,-,3,5,000,1,9,000],[B,-,7,3,000,5,6,000],[C,A,9,7,000,8,12,000],[D,A, B,11,8,000,9,14,000],[E,B,2,5,000,2,5,000],[F,D,8,1,000,5,7,000],[G,E, F,2,3,000,1,9,000],[H,G,8,3,500,7,4,500],[I,C, F,9,3,000,8,7,000]] a.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!