Question: table [ [ Activity Immediate Predecessor ( s ) , table [ [ Normal ] , [ Time ( weeks ) ] ]
tableActivity Immediate PredecessorstableNormalTime weekstableNormalCost $tableCrashTime weekstableCrashCost $ABCADA BEBFDGE FHGIC F
a What is the critical path based on the normal time?
A
B BDFI
C BEGH
D ADFGH
b What is the project duration based on the normal times? weeks.
c Calculate different project costs based on the normal times.
Total direct costs total normal costs: $
Total indirect costs: $
Total penalty costs: $
d To reduce the project duration by week, which activity should we crash to minimize the project costs?
A Activity D
B Activity G
C Activity B
D Activity
E Activity
e What are the various project costs after crashing the activity you selected in part d
Total direct costs total normal costs: $
Total indirect costs; $
Total penalty costs: $
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
