Question: table [ [ Activity , Immediate Predecessor ( s ) , table [ [ Time ] , [ ( weeks ) ] ]

\table[[Activity,Immediate Predecessor(s),\table[[Time],[(weeks)]]],[S,-,5],[T,-,7],[U,S,4],[V,S,3],[W,T. U,7],[X,T,7],[Y,V. W,3],[Z,X,2]]
a) Choose the correct project network.
A.
c.
b) The critical path is
The project completion time is weeks (enter your response as a whole number).
 \table[[Activity,Immediate Predecessor(s),\table[[Time],[(weeks)]]],[S,-,5],[T,-,7],[U,S,4],[V,S,3],[W,T. U,7],[X,T,7],[Y,V. W,3],[Z,X,2]] a) Choose the correct project network. A.