Question: table [ [ Activity , Immediate Predecessors,Optimistic,Most Likely,Pessimistic ] , [ A , - - , 3 , 3 , 7 ] , [

\table[[Activity,Immediate Predecessors,Optimistic,Most Likely,Pessimistic],[A,--,3,3,7],[B,A,4,6,10],[C,A,5,7,10],[D,A,3,11,12],[E,B,2,4,6],[F,B,5,8,10],[G,C, F,5,8,9],[H,D,2,5,9],[I,H,6,8,12],[J,G, I,6,5,11],[K,,5,,]]
Draw the network diagram by using Activity on Node method (5 pt).
Label each activity time under each node (5pt.
 \table[[Activity,Immediate Predecessors,Optimistic,Most Likely,Pessimistic],[A,--,3,3,7],[B,A,4,6,10],[C,A,5,7,10],[D,A,3,11,12],[E,B,2,4,6],[F,B,5,8,10],[G,C, F,5,8,9],[H,D,2,5,9],[I,H,6,8,12],[J,G, I,6,5,11],[K,,5,,]] Draw the network diagram by using