Question: table [ [ Activity , Immediate,Time in , ] , [ Break down both machines,Designation,Predecessor,Days ] , [ Clean machine 1 , A ,

\table[[Activity,Immediate,Time in,],[Break down both machines,Designation,Predecessor,Days],[Clean machine 1,A,None,3],[Clean machine 2,B,A,3],[Re-set machine,C,A,3],[Re-set machine,D,B,1],[Re-calibrate both machines,E,C,2],[Final test,F,D and E,1],[Fing,G,F,2]]
Using CPM, what is the Latest Finish Time for the last activity in this project (i.e., the total time to complete the project)?
 \table[[Activity,Immediate,Time in,],[Break down both machines,Designation,Predecessor,Days],[Clean machine 1,A,None,3],[Clean machine 2,B,A,3],[Re-set machine,C,A,3],[Re-set machine,D,B,1],[Re-calibrate

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!