Question: table [ [ Activity , Norm Time,Crash Time,Crash $ , Normal $ , Predecessors ] , [ A , 3 , 2 , 4

\table[[Activity,Norm Time,Crash Time,Crash $,Normal $,Predecessors],[A,3,2,45000,30000,],[B,8,5,210000,150000,A],[C,3,2,50000,40000,B],[D,5,3,70000,60000,A],[E,4,2,30000,25000,B],[F,2,1,27,000,18,000,],[G,3,2,28000,20000,D, E],[H,3,2,21000,15000,F],[I,2,20000,20000,G,]]
a. What is the project length?
b. What activities are on the critical path?
c. What activity should be crashed first and what is the cost?
d. What is the maximum that can be crashed from the project and what is the total cost?
 \table[[Activity,Norm Time,Crash Time,Crash $,Normal $,Predecessors],[A,3,2,45000,30000,],[B,8,5,210000,150000,A],[C,3,2,50000,40000,B],[D,5,3,70000,60000,A],[E,4,2,30000,25000,B],[F,2,1,27,000,18,000,],[G,3,2,28000,20000,D, E],[H,3,2,21000,15000,F],[I,2,20000,20000,G,]] a. What is the project

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!