Question: table [ [ Activity , Precedes, table [ [ Time ] , [ Estima ] , [ tes ] , [ ( days

\table[[Activity,Precedes,\table[[Time],[Estima],[tes],[(days)]]],[Optimistic,Most Likely,Pessimistic],[Start,A,-,-,-],[A,B, C,49,49,61],[B,D,80,95,98],[C,E,91,100,115],[D,F,37,39,49],[E,End,42,48,66],[F,End,62,65,80]]
What is the standard deviation of path A-B-D-F?
9.06 days
6.40 days
6.16 days
7.55 days
7.07 days
 \table[[Activity,Precedes,\table[[Time],[Estima],[tes],[(days)]]],[Optimistic,Most Likely,Pessimistic],[Start,A,-,-,-],[A,B, C,49,49,61],[B,D,80,95,98],[C,E,91,100,115],[D,F,37,39,49],[E,End,42,48,66],[F,End,62,65,80]] What is the standard deviation of path A-B-D-F?