Question: table [ [ Activity , Predecessor, table [ [ Crash Cost ] , [ ( Slope ) ] ] , table [

\table[[Activity,Predecessor,\table[[Crash Cost],[(Slope)]],\table[[Maximum Crash],[Time]],Normal Time,Normal Cost],[A,None,30,1,5,40],[B,A,60,2,6,50],[C,A,50,1,4,80],[D,A,0,0,12,50],[E,B,70,4,7,100],[F,C,120,1,3,40],[G,D, E, F,90,,3,100]]
Question 7
The total cost for 19 time units of project duration is $
880
910
850
940
 \table[[Activity,Predecessor,\table[[Crash Cost],[(Slope)]],\table[[Maximum Crash],[Time]],Normal Time,Normal Cost],[A,None,30,1,5,40],[B,A,60,2,6,50],[C,A,50,1,4,80],[D,A,0,0,12,50],[E,B,70,4,7,100],[F,C,120,1,3,40],[G,D, E, F,90,,3,100]] Question 7 The total