Question: table [ [ activity predecessors normal _ time crash _ time ] , [ A , , 2 , 2 , 4 5 0

\table[[activity predecessors normal_time crash_time],[A,,2,2,4500,4500],[B,A,5,2,3500,6500],[C,B,2,2,2000,2000],[D,C,2,2,3000,3000],[E,B,5,2,4500,13500],[F,E,3,1,5500,13500]]
The table shows normal time, crash time, normal cost, crash cost of activities in a project. According to this table which activity must be crashed first? (Only enter the name of the activity. Lower or uppercase both work. Ex: A or a. Copyrighted content. Cannot be posted. Oorsdemir)
 \table[[activity predecessors normal_time crash_time],[A,,2,2,4500,4500],[B,A,5,2,3500,6500],[C,B,2,2,2000,2000],[D,C,2,2,3000,3000],[E,B,5,2,4500,13500],[F,E,3,1,5500,13500]] The table shows normal time, crash time,

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!