Question: table [ [ Activity , table [ [ Predecessor ] , [ Activity ] ] , table [ [ Optimistic ] ,

\table[[Activity,\table[[Predecessor],[Activity]],\table[[Optimistic],[estimate of],[time]],\table[[Most likely],[estimate of],[time]],\table[[Pessimistic],[estimate of],[time]]],[A,-,2,4,6],[B,A,8,11,20],[C,A,10,15,20],[D,B,12,18,24],[E,C,8,13,24],[F,C,4,7,16],[G,D,F,14,18,28],[H,E,10,12,14],[I,G,H,7,10,19]]
 \table[[Activity,\table[[Predecessor],[Activity]],\table[[Optimistic],[estimate of],[time]],\table[[Most likely],[estimate of],[time]],\table[[Pessimistic],[estimate of],[time]]],[A,-,2,4,6],[B,A,8,11,20],[C,A,10,15,20],[D,B,12,18,24],[E,C,8,13,24],[F,C,4,7,16],[G,D,F,14,18,28],[H,E,10,12,14],[I,G,H,7,10,19]]