Question: table [ [ Activity , table [ [ Duration ] , [ ( weeks ) ] ] , Dependency,Resources ] , [ A
tableActivitytableDurationweeksDependency,ResourcesABACADAEBFBGCHEIEFGJHKI,JLDGK
a Draw a project network from the table above
b
i What activitys is a burst activity?
ii What activitys is a merge activity?
iii. What is the length of the project?
iv What is the critical path?
c Draw the Gantt chart
d Assuming there are only resources available for the duration of this project, how can the schedule ble best adjusted to level the resources?
e Revise the Gantt chart to reflect this resource availability.