Question: table [ [ Activity , table [ [ Expected Time ] , [ ( days ) ] ] , Critical ] , [

\table[[Activity,\table[[Expected Time],[(days)]],Critical],[A,15,YES],[B,4,NO],[C,10,YES],[D,8,YES],[E,6,YES],[F,12,YES],[G,7,NO],[H,10,NO]]
What is the expected completion time of this project?
51
52
62
55
53