Question: table [ [ Activity , table [ [ optimistic ] , [ time ] ] , table [ [ most likely ]

\table[[Activity,\table[[optimistic],[time]],\table[[most likely],[time]],\table[[pessimistic],[time]],\table[[Activity],[Predecessor]]],[A,3,5,7,-],[B,4,8,10,A],[C,2,3,5,A],[D,6,9,12,B, C],[E,5,9,15,D]]
Table 1
Reference: Ref 1
Using Table 1, the probability that the project could be completed in 34 weeks or less is approximately
A.0.86.
B.0.89.
C.0.96.
D.0.91.
 \table[[Activity,\table[[optimistic],[time]],\table[[most likely],[time]],\table[[pessimistic],[time]],\table[[Activity],[Predecessor]]],[A,3,5,7,-],[B,4,8,10,A],[C,2,3,5,A],[D,6,9,12,B, C],[E,5,9,15,D]] Table 1 Reference: Ref 1 Using Table 1,