Question: table [ [ Activity , table [ [ Normal Time ] , [ ( weeks ) ] ] , table [ [

\table[[Activity,\table[[Normal Time],[(weeks)]],\table[[Crash Time],[(weeks)]],\table[[Normal],[Cost]],\table[[Total Cost],[with],[Crashing]],\table[[Immediate],[Predecessor(s)]]],[A,4,3,$2,000,$2,600,-],[B,2,1,$2,100,$2,800,-],[C,3,3,$500,$500,-],[D,8,4,$2,500,$2,780,A],[E,6,3,$1,000,$1,375,B],[F,3,2,$3,400,$4,900,C],[G,4,2,$1,500,$2,000,D, E]]
a) Based on the given information regarding the activities for the project, the project length =16 weeks
b) The total cost required for completing this project on normal time = :
c) For reducing the duration of the project by one week, the activity that should be crashed first is activity D .
The cost of the project based on the first activity selected for crashing will increase by $70.
d) The maximum weeks by which the project can be reduced by crashing = weeks.
Total cost of crashing the project to minimum (or maximum weeks possible)=$
 \table[[Activity,\table[[Normal Time],[(weeks)]],\table[[Crash Time],[(weeks)]],\table[[Normal],[Cost]],\table[[Total Cost],[with],[Crashing]],\table[[Immediate],[Predecessor(s)]]],[A,4,3,$2,000,$2,600,-],[B,2,1,$2,100,$2,800,-],[C,3,3,$500,$500,-],[D,8,4,$2,500,$2,780,A],[E,6,3,$1,000,$1,375,B],[F,3,2,$3,400,$4,900,C],[G,4,2,$1,500,$2,000,D, E]] a) Based on the given information

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!