Question: table [ [ Activity , table [ [ Immediate ] , [ Predecessor ] ] , Time ( months ) ] , [
tableActivitytableImmediatePredecessorTime monthsANone,BNone,CA BDBEDFACGEFHG
Determine the critical path of this project.
Determine the total project completion time.
Complete the following table so as to determine the forward and backward passes of this project.