Question: table [ [ Activity , table [ [ Immediate ] , [ Predecessor ( s ) ] ] , table [ [

\table[[Activity,\table[[Immediate],[Predecessor(s)]],\table[[Most],[Optimistic]],\table[[Most],[Likely]],\table[[Most],[Pessimistic]]],[A,-,2,4,6],[B,A,1,4,7],[C,B,2,2,2],[D,D,1,7,10],[E,E,2,4,6],[F,C,1,2,3],[G,D,G,3,4,17],[H,D,3,7,11],[I,F,H,8,9,10],[J,I,4,5,6]]
Using Table 7.12 what is the earliestexpected time of completion of the whole project?
greater than 22 but fewer than or equal to 23 days
(B) greater than 21 but fewer than or equal to 22 days
greater than 23 days
fewer than or equal to 21 days
 \table[[Activity,\table[[Immediate],[Predecessor(s)]],\table[[Most],[Optimistic]],\table[[Most],[Likely]],\table[[Most],[Pessimistic]]],[A,-,2,4,6],[B,A,1,4,7],[C,B,2,2,2],[D,D,1,7,10],[E,E,2,4,6],[F,C,1,2,3],[G,D,G,3,4,17],[H,D,3,7,11],[I,F,H,8,9,10],[J,I,4,5,6]] Using Table 7.12 what is the earliestexpected time of completion

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!