Question: table [ [ Activity , table [ [ Normal ] , [ Time ] , [ ( weeks ) ] ] ,

\table[[Activity,\table[[Normal],[Time],[(weeks)]],\table[[Crash],[Time],[(weeks)]],\table[[Normal],[Cost]],Crash Cost,\table[[Immediate],[Predecessor(s)]]],[A,4,3,$2,000,$2,600,-],[B,2,1,$2,200,$2,800,-],[C,4,3,$500,$800,-],[D,8,5,$2,300,$2,600,A, B],[E,6,3,$900,$1,200,C],[F,3,2,$3,000,$4,200,D, E],[G,4,2,$1,400,$2,000,E, F]]
a. What is the critical path
b. What is the project length?
c. If you wish to reduce the time required to complete this project by 1 week, which activity should be crashed, and how much will this increase the total cost?
d. If you wish to take another week off the project, which activity would you choose and what is the total cumulative cost?
e. What is the maximum time that can be crashed?
q, How much would costs increase? $
 \table[[Activity,\table[[Normal],[Time],[(weeks)]],\table[[Crash],[Time],[(weeks)]],\table[[Normal],[Cost]],Crash Cost,\table[[Immediate],[Predecessor(s)]]],[A,4,3,$2,000,$2,600,-],[B,2,1,$2,200,$2,800,-],[C,4,3,$500,$800,-],[D,8,5,$2,300,$2,600,A, B],[E,6,3,$900,$1,200,C],[F,3,2,$3,000,$4,200,D, E],[G,4,2,$1,400,$2,000,E, F]] a. What is the critical path

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!