Question: table [ [ Activity , table [ [ Immediate ] , [ Predecessors ] ] , table [ [ Normal ] ,

\table[[Activity,\table[[Immediate],[Predecessors]],\table[[Normal],[Duration],[(months)]],\table[[Normal cost],[($)]]],[A,-,3,700],[B,-,4,900],[C,A,2,1,100],[D,B,6,600],[E,C, D,8,800],[F,D,7,1,300],[G,E,4,500],[H,E, F,9,800]]
A) Draw a network diagram for this project.
 \table[[Activity,\table[[Immediate],[Predecessors]],\table[[Normal],[Duration],[(months)]],\table[[Normal cost],[($)]]],[A,-,3,700],[B,-,4,900],[C,A,2,1,100],[D,B,6,600],[E,C, D,8,800],[F,D,7,1,300],[G,E,4,500],[H,E, F,9,800]] A) Draw a network diagram for this