Question: table contains relevant information about the activities. begin { tabular } { | c | c | c | c | c | c
table contains relevant information about the activities.
begintabularccccccc
cline multicolumnc & multicolumnc Time weeks & multicolumnc Cost $s
hline Activity & Description & begintabularc
Immediate
Predecessor
endtabular & Normal & Crash & Normal & Crash
hline A & Plan needs & & & & &
hline B & Order equipment & A & & & &
hline C & Install equipment & B & & & &
hline D & Set up training lab & A & & & &
hline E & Conduct training course & D & & & &
hline F & Test system & C E & & & &
hline
endtabular
a Develop a project network.
ib Develop an activity schedule.
c What are the critical activities? Enter your answers as a commaseparated list.
What is the expected project completion time in weeks
weeks
d Assume that the company wants to complete the project in six months or weeks. What is the amount of crash time in weeks for each activity that minimizes cost?
A B C D Equad
e Develop an activity schedule for the crashed project.
f What added project cost in thousands of dollars is required to meet the sixmonth completion time? thousands of dollars
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock