Question: table [ [ , DAYS,IMMEDIATE, ] , [ ACTIVITY , a , m , b , PREDECESSORS ] , [ A , 3 ,

\table[[,DAYS,IMMEDIATE,],[ACTIVITY,a,m,b,PREDECESSORS],[A,3,6,9,-],[B,2,4,6,-],[C,1,2,3,-],[D,6,7,8,C],[E,2,4,6,B, D],[F,6,10,14,A, E],[G,1,2,6,A, E],[H,3,6,9,F],[I,10,11,12,G],[J,14,16,21,G],[K,2,8,11,H, I]]
(a) Develop a project network for this problem.
(b) Determine the expected duration and variance for each activity.
(c) Determine the ES, EF, LS, LF, and slack time for each activity. Also determine the total project completion time and critical path(s).
(d) What is the probability that this job will finish in 38 days or less?
 \table[[,DAYS,IMMEDIATE,],[ACTIVITY,a,m,b,PREDECESSORS],[A,3,6,9,-],[B,2,4,6,-],[C,1,2,3,-],[D,6,7,8,C],[E,2,4,6,B, D],[F,6,10,14,A, E],[G,1,2,6,A, E],[H,3,6,9,F],[I,10,11,12,G],[J,14,16,21,G],[K,2,8,11,H, I]] (a) Develop a project network for

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!