Question: table [ [ , Duration ( days ) , Predecessor ] , [ , B , - ] , [ , 1 0 ,

\table[[,Duration (days),Predecessor],[,B,-],[,10,A],[,5,A],[,14,A],[,20,B],[,4,C],[,2,D],[,21,E],[,17,E],[,11,G],[,30,I]]
Use the abowe-mentioned information to do the following.
a. Construct a project network diagram.
b. Determine all the paths through the diagram and their duration.
c. Determine the critical path and its duration.
 \table[[,Duration (days),Predecessor],[,B,-],[,10,A],[,5,A],[,14,A],[,20,B],[,4,C],[,2,D],[,21,E],[,17,E],[,11,G],[,30,I]] Use the abowe-mentioned information to do the following. a.