Question: table [ [ F , C , 3 ] , [ G , B , C , 5 ] , [ H , F
tableFCGB CJD HKG HLE GMNL MPJ KQL NRP Q
Based on the information given in the case, answer the following questions. Show all work that you need to arrive at your answers.
a Develop the activity precedence diagram.
b Determine the minimum cycle time, the maximum cycle time.
c What will be the producaton rate per day if minimum cycle time is used? maximum cycle time is used?
d In order to meet the projected demand what should be the cycle time?
e What is the theoretical number of minimum workstations?
f Assign work elements according to the most following tasks rule.
g Assign work elements according to the greatest positional weight rule.
h Assign work elements according to the shortest processing time rule.