Question: table [ [ ID , Description,Predecessor, table [ [ Time ] , [ ( days ) ] ] ] , [ A ,

\table[[ID,Description,Predecessor,\table[[Time],[(days)]]],[A,Systems,None,8],[B,Subsystem A design,A,1],[C,Subsystem B design,A,2],[D,Subsystem C design,A,1],[E,Program A,B,2],[F,Program B,C,14],[G,Program C,D,2],[H,Subsystem A test,E,4],[I,Subsystem B test,F,3],[J,Subsystem C test,G,4],[K,Integration,H, I, J,],[L,Integration test,K,2],[,,,]]
Calculate the free slack and total slack for all noncritical activities
There is total slack on activities B,D,E,G,H, and J and free slack on activities H and J.
How sensitive is the network schedule? Not very sensitive. There is a single dominant critical path.
\table[[What is the total slack on D?,days.],[What is the total slack on E?,],[What is the FREE slack on B?,],[What is the FREE slack on H?,day(s).]]
 \table[[ID,Description,Predecessor,\table[[Time],[(days)]]],[A,Systems,None,8],[B,Subsystem A design,A,1],[C,Subsystem B design,A,2],[D,Subsystem C design,A,1],[E,Program A,B,2],[F,Program B,C,14],[G,Program C,D,2],[H,Subsystem A

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!