Question: table [ [ JOB , DUE,DURATION ( DAYS ] , [ , DATE ( DAYS ) , REQUIRED ) ] , [ Alter piece

\table[[JOB,DUE,DURATION (DAYS],[,DATE (DAYS),REQUIRED)],[Alter piece (A),31,4],[Baptist Church (B),51,17],[Church of Christ (C),270,110],[Deacon's window (D),61,15],[Entry way (special order)(E),76,30],[Frank's Construction (kitchen window)(F),106,20]]
a) Sequence the jobs according to the following decision rules: FCFS, EDD, SPT, and LPT.
According to the FCFS rule, the sequence of jobs should be
According to the EDD rule, the sequence of jobs should be A,B,D,E,F,C.
According to the SPT rule, the sequence of jobs should be .
According to the LPT rule, the sequence of jobs should be
b), c), d) & e) Compute the average completion (flow) time, average lateness, and average number of jobs in the system for each rule.
Construct the table of measures of effectiveness for each rule (round your responses to two decimal places).
\table[[Rule,\table[[Average],[Completion (Flow)],[Time]],Average Lateness,\table[[Average Number of Jobs],[in System]]],[FCFS,,,],[EDD,,,],[SPT,,,],[LPT,,,]]
f) Which is the best decision rule based on average completion (flow) time?
The best decision rule based on average completion (flow) time is
g) Which is the best decision rule based on average lateness?
The best decision rule based on average lateness is
 \table[[JOB,DUE,DURATION (DAYS],[,DATE (DAYS),REQUIRED)],[Alter piece (A),31,4],[Baptist Church (B),51,17],[Church of Christ (C),270,110],[Deacon's window

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!