Question: table [ [ Job , Immediate Predecessors,Time Required ( Weeks ) ] , [ A , - , 3 ] , [ B ,

\table[[Job,Immediate Predecessors,Time Required (Weeks)],[A,-,3],[B,-,5],[C,-,2],[D,-,4],[E,B, C,9],[F,C,7],[G,A, D, E,4],[H,E,5],[I,E, F,6]]A certain project is made up of nine jobs. The associated precedence requirements and job processing times are as follows:
Job Immediate Predecessors Time Required (Weeks)
A -3
B -5
C -2
D -4
E B, C 9
F C 7
G A, D, E 4
H E 5
I E, F 6
Which is the least critical job to the project (i.e., which job has the greatest slack)?
 \table[[Job,Immediate Predecessors,Time Required (Weeks)],[A,-,3],[B,-,5],[C,-,2],[D,-,4],[E,B, C,9],[F,C,7],[G,A, D, E,4],[H,E,5],[I,E, F,6]]A certain project is

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!