Question: table [ [ Job , Processing Time ( hrs ) , Hours Until Due ] , [ A , 1 0 , 2 ]

\table[[Job,Processing Time (hrs),Hours Until Due],[A,10,2],[B,5,4],[C,7,5],[D,3,6],[E,1,7]]
What is the throughput time for the optimal schedule?
28 hours
25 hours
50 hours
24 hours
26 hours
 \table[[Job,Processing Time (hrs),Hours Until Due],[A,10,2],[B,5,4],[C,7,5],[D,3,6],[E,1,7]] What is the throughput time for