Question: table [ [ Job , Processing Time ( hrs ) , Hours Until Due ] , [ V , 3 , 5 ] ,

\table[[Job,Processing Time (hrs),Hours Until Due],[V,3,5],[x,1,1],[Y,4,9],[Z,2,3]]
If Eva uses the shortest processing time first (SPT) priority rule to schedule these jobs, what will be the average completion time?
(A)8 hours
3 hours
7 hours
(D)7.2 hours
(E)5 hours