Question: table [ [ , Lot size,Run time,Setup time ] , [ Machine 1 , 2 0 , 4 , 2 2 ] , [

\table[[,Lot size,Run time,Setup time],[Machine 1,20,4,22],[Machine 2,15,5,15],[Machine 3,35,5,10]]
\table[[Legs,,,],[,Lot size,Run time,Setup],[Machine 1,20,5,25],[Machine 2,30,6,15],[Machine 3,22,4,20]]
The master production schedule for next week has a quantity of 15 desks.
In order to make one desk, what is the capacity requirement from Machine 1 minutes?
 \table[[,Lot size,Run time,Setup time],[Machine 1,20,4,22],[Machine 2,15,5,15],[Machine 3,35,5,10]] \table[[Legs,,,],[,Lot size,Run time,Setup],[Machine 1,20,5,25],[Machine