Question: table [ [ No , ACT,DUR,PREDECESSORS ] , [ 5 , B , 5 , ] , [ 1 0 , M , 4

\table[[No,ACT,DUR,PREDECESSORS],[5,B,5,],[10,M,4,B],[15,N,9,B],[20,x,15,B],[25,A,5,M,N],[30,F,6,N,x],[35,Q,2,x],[40,C,4,x],[45,Y,10,A],[50,S,10,F,A],[55,R,2,Q,F],[60,T,5,C,Q],[65,K,7,Y,S,R],[70,U,3,K,T]]
Determine the TF (Days) of the activity "M" in this Project based on the following table:
( Construct an AON diagram. On the diagram, compute the four schedule dates (ESD, EFD, LSD, and LFD) and the floats (TF, FF) for each activity)
Your Answer:
Answer
 \table[[No,ACT,DUR,PREDECESSORS],[5,B,5,],[10,M,4,B],[15,N,9,B],[20,x,15,B],[25,A,5,M,N],[30,F,6,N,x],[35,Q,2,x],[40,C,4,x],[45,Y,10,A],[50,S,10,F,A],[55,R,2,Q,F],[60,T,5,C,Q],[65,K,7,Y,S,R],[70,U,3,K,T]] Determine the TF (Days) of the activity "M" in this

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!