Question: Table Programme project table [ [ Activity , , table [ [ Preceding ] , [ activities ] ] , table [

Table
Programme project
\table[[Activity,,\table[[Preceding],[activities]],\table[[Duration],[(days)]]],[A,Book individual dates for programme,-,12],[B,Contact key speakers to agree availability,A,14],[C,Arrange sponsorship to help with costs,-,4],[D,Send out membership renewal details,-,6],[E,Membership renewals returned,D,7],[F,\table[[Send reminder notice to those who have],[not renewed membership together with],[list of key speakers]],R.F,],[G,Membership renewals returned,F,F,\table[[11],[10]]],[H,Compile membership list,G,18],[l,Print detailed programme,B, C,6],[J,Mail final programme to members,I, G,18]]
(a) The critical path from the project is A,B,F,G,H,J.
(b) Overall completion time is days.
 Table Programme project \table[[Activity,,\table[[Preceding],[activities]],\table[[Duration],[(days)]]],[A,Book individual dates for programme,-,12],[B,Contact key speakers to

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!