Question: Table Q 1 below shows activities for a small project from ABLOY Company. Based on the information given in Table Q 1 , answer the

Table Q1 below shows activities for a small project from ABLOY Company. Based on the information given in Table Q1, answer the questions given below.
Table Q1
\table[[Activity,\table[[Immediate],[Predecessor(s)]],Direct Cost,],[Normal,Crash],[,,Time (week),Cost (RM),Time (week),Cost (RM)],[A,-,3,1,600,2,1,800],[B,-,4,2,000,3,2,400],[C,-,7,600,5,750],[D,A,4,1,200,3,1,700],[E,B,4,800,3,1,100],[F,C,5,3,400,4,3,500],[G,D,E,5,2,200,3,2,900],[H,D,E,6,2,600,3,2,900],[I,G,8,1,600,5,2,050],[J,F,H,4,1,800,3,2,000],[K,I.J,3,1,750,2,1,850]]
a. Construct the network for the project crashing. Determine the paths and the critical path for the project with their expected completion time for each path. Calculate the total project cost and acceleration cost per time period for each activity.
(20 marks)
(CLO4:PLO5:C4)(WP1)
b. The management of ABLOY Company instructed that the activities should be crashed to 21 weeks project completion time. This is due to the pressure on moving the resources to the other project. Decide the new activities time and cost. You are required to show all calculation crashing steps from the actual project completion time to the 21 weeks of the project crashing.
(10 marks)(CLO4:PLO5:C5)(WP6, WK6)
 Table Q1 below shows activities for a small project from ABLOY

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!