Question: Table Q 1 below shows activities for a small project from ABLOY Company. Based on the information given in Table Q 1 , answer the
Table Q below shows activities for a small project from ABLOY Company. Based on the information given in Table answer the questions given below.
Table Q
tableActivitytableImmediatePredecessorsDirect Cost,NormalCrashTime weekCost RMTime weekCost RMABCDAEBFCGDEHDEIGJFHKI.J
a Construct the network for the project crashing. Determine the paths and the critical path for the project with their expected completion time for each path. Calculate the total project cost and acceleration cost per time period for each activity.
marks
CLO:PLO:CWP
b The management of ABLOY Company instructed that the activities should be crashed to weeks project completion time. This is due to the pressure on moving the resources to the other project. Decide the new activities time and cost. You are required to show all calculation crashing steps from the actual project completion time to the weeks of the project crashing.
marksCLO:PLO:CWP WK
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock