Question: table [ [ { table [ [ MAJOR SUBPROJECTS / ACTIVITIES ] , [ Product Specifications ( P ) ] ] } ]
table
tableMAJOR SUBPROJECTSACTIVITIESProduct Specifications PMarket research,POverall product specifications,PPHardwarePPSoftwarePPSupplier specifications SHardwareSPSoftwareSPProduct design DDSDisplayDSCameraDSProduct integration IHardwareIDUser interface,IDSoftware coding,IIPrototype testing,IIISubcontracting VSuppliers selection,VS SContract negotiation,VI V a Calculate the start and finish times for each activity. Leave no cells blank be certain to enter O wherever required.
tableActivityEarliest Start Time,Earliest Finish Time,Latest Start Time,Latest Finish TimePPPPSSDDDDIIIVVYou work for a company that makes cell phones and have been made project manager for the
design of a new cell phone. Your supervisors have already scoped the project, so you have a
list showing the work breakdown structure, and this includes major project activities. You must
plan the project schedule and calculate project duration. Your boss wants the schedule on his
desk tomorrow morning!
You have been given the information in Exhibit It includes all the activities required in
the project and the duration of each activity. Also, dependencies between the activities have
been identified. Remember that the preceding activity must be fully completed before work on
the following activity can be started.
Your project is divided into five major subprojects. Subproject involves developing
specifications for the new cell phone. Here, decisions related to such things as battery life, size
of the phone, and features need to be made. These details are based on how a customer uses
the cell phone. These user specifications are redefined in terms that have meaning to the
subcontractors that will actually make the new cell phone in subproject supplier
specifications. These involve engineering details for how the product will perform.
The individual components that make up the product are the focus of subproject D
Subproject I brings all the components together, and a working prototype is built and tested.
Finally, in subproject suppliers are selected and contracts are negotiated.
Exhibit : Work Breakdown Structure and Activities for the Cell Phone Design Project
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock