Question: table [ [ Task Description, table [ [ Task Duration In ] , [ Hrs / Mins ] ] , ] , [

\table[[Task Description,\table[[Task Duration In],[Hrs/Mins]],],[(Task #01) Cutting of MDF boards process.,0:45:00,N/A],[(Task #02) Filling and sanding process.,0:25:00,Task #01],[(Task #03) Fabrication of metal work/welding,0:45:00,N/A],[(Task #04) Painting process of metal frame work.,1:00:00,Task #03],[(Task #05) Assemble of unit/workstation.,1:05:00,Task #01, #02, #03 #04],[(Task #06) Electrical Installation of components.,1:16:00,Task #05],[(Task #07) Packaging process of finish product.,0:50:00,Task #01, #02, #03, #04, #05, #06,]]
Table 1
Using Table 1 above calculate the EST and the LFT also sketch a detail critical path diagram.
 \table[[Task Description,\table[[Task Duration In],[Hrs/Mins]],],[(Task #01) Cutting of MDF boards process.,0:45:00,N/A],[(Task #02)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!