Question: table [ [ Task , Immediate predecessor,Task time ( min ) ] , [ A , - , 1 2 ] , [ B

\table[[Task,Immediate predecessor,Task time (min)],[A,-,12],[B,A,6],[C,B,6],[D,B,2],[E,B,2],[F,B,12],[G,C, D,7],[H,G,5],[I,E,1],[J,F, I,4],[K,H, J,6],[L,K,7]]
Demand rate =140 units/week
Assembly operates for 1 shift/day (7 hours),5 days a week.
i. Draw a precedence diagram,
ii. Design an assembly line,
iii. Find line efficiency
 \table[[Task,Immediate predecessor,Task time (min)],[A,-,12],[B,A,6],[C,B,6],[D,B,2],[E,B,2],[F,B,12],[G,C, D,7],[H,G,5],[I,E,1],[J,F, I,4],[K,H, J,6],[L,K,7]] Demand rate =140 units/week