Question: table [ [ Task , Precendence,Time taken ] , [ A Themes and ideas discussed, - , 1 week ] , [ B Advertising

\table[[Task,Precendence,Time taken],[A Themes and ideas discussed,-,1 week],[B Advertising sold,-,4 weeks],[C Advertisements written,B,3 weeks],[D Research for articles,A,2 weeks],[E Reporters conduct interviews,D,3 weeks],[F Photographs and images,D,3 weeks],[G Articles written and edited,E,2 weeks],[H Layout and design on the computer,C, F, G,2 weeks],[I Proof reading,H,0.5 week],[J Newspaper is published and delivered,I,0.5 week]].
Use critical path analysis and the information in the precedence table to prepare a report on the
process of producing a school newspaper. Recommend the number of groups that need to work
on this project and how the tasks could be allocated to the groups.
The report should include:
a network diagram showing the tasks in the project
the tasks in the critical path of the project
the minimum length of time required to complete the project
the start and finish time for each task
the allocation of tasks to a minimum number of groups
a recommendation of when the school principal could visit the class to see at least three
different tasks in action
a discussion of any other factors that could significantly delay the publication of the
newspaper.
An important news story comes to the attention of the class shortly before the paper goes to
print. The class would like to include a new article in the newspaper which will delay task G
.
Discuss the effect of this delay on the production deadline for the newspaper.
 \table[[Task,Precendence,Time taken],[A Themes and ideas discussed,-,1 week],[B Advertising sold,-,4 weeks],[C Advertisements

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!