Question: table [ [ Task , Predecessor,Optimistic,Most Likely,Pessimistic ] , [ A , - , 5 , 8 , 1 0 ] , [ B
tableTaskPredecessor,Optimistic,Most Likely,PessimisticABACBDED
Using Table what is the probability that the project will take or more weeks to complete?
A less than or equal to
B greater than
greater than but less than or equal to
D greater than but less than or equal to
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
