Question: table [ [ Task , Predecessor,Optimistic,Most Likely,Pessimistic ] , [ A , - , 5 , 8 , 1 0 ] , [ B

\table[[Task,Predecessor,Optimistic,Most Likely,Pessimistic],[A,-,5,8,10],[B,A,7,10,12],[C,B,8,10,14],[D,-,11,15,18],[E,D,12,14,18]]
Using Table 7.14, what is the probability that the project will take 16 or more weeks to complete?
(A) less than or equal to 20%
(B) greater than 30%
greater than 25% but less than or equal to 30%
(D) greater than 20% but less than or equal to 25%
 \table[[Task,Predecessor,Optimistic,Most Likely,Pessimistic],[A,-,5,8,10],[B,A,7,10,12],[C,B,8,10,14],[D,-,11,15,18],[E,D,12,14,18]] Using Table 7.14, what is the probability that the