Question: table [ [ , Time ( days ) , Immediate ] , [ Activity , a , m , b , Predecessor ( s

\table[[,Time (days),Immediate],[Activity,a,m,b,Predecessor(s)],[A,4,7,8,-],[B,4,5,6,-],[C,2,3,4,-],[D,7,8,9,C],[E,3,5,7,B, D],[F,7,10,14,A, E],[G,1,2,3,A, E],[H,5,7,9,F],[I,11,12,13,G],[J,15,17,19,C],[K,3,7,11,H, I]]
Based on the activity time estimates, the expected times and variance for each of the activities are:
(Round your responses to two decimal places.)
\table[[Activity,Expected Time,Variance],[A,,],[B,-,],[C,,],[D,,],[E,,],[F,,],[G,,],[H,,],[I,,],[J,,],[K,,]]
 \table[[,Time (days),Immediate],[Activity,a,m,b,Predecessor(s)],[A,4,7,8,-],[B,4,5,6,-],[C,2,3,4,-],[D,7,8,9,C],[E,3,5,7,B, D],[F,7,10,14,A, E],[G,1,2,3,A, E],[H,5,7,9,F],[I,11,12,13,G],[J,15,17,19,C],[K,3,7,11,H, I]] Based on the activity time

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!